- Drill Rig Schedule - [175 activities]
Drill Rig Schedule - [175 activities]
Onshore Drilling Rig Primavera P6 XER Template – 3-Well Pad Development
Develop quality schedules faster with this professionally developed Primavera P6 XER Template designed for a typical 3-well-pad onshore drilling project.
Featuring 175 professionally developed, logic-linked activities, this template provides a structured scheduling framework covering the major phases of drilling operations—from rig mobilization through drilling, casing, cementing, logging, rig release, and demobilization.
Whether you're preparing a bid schedule, developing a baseline, or creating a project execution schedule, this template provides an excellent starting point while significantly reducing schedule development time.
What's Included
- Primavera P6 XER file
- 175 logic-linked activities
- Organized Work Breakdown Structure (WBS)
- Complete activity logic and relationships
- Major project milestones
- Ready for Primavera P6 import
- Fully editable and customizable
Typical Scope
The schedule represents a typical onshore drilling program for a 3-well-pad development, including:
- Rig mobilization
- Rig-up and commissioning
- Surface drilling
- Intermediate drilling
- Production hole drilling
- Casing operations
- Cementing operations
- Directional drilling support
- Wireline logging
- Wellhead installation
- Rig-down
- Rig demobilization
- Project closeout milestones
Ideal For
- Oil & Gas Operators
- Drilling Contractors
- EPC Contractors
- Project Controls Professionals
- Planning & Scheduling Engineers
- Construction Managers
- Project Managers
- Consultants
Benefits
- Save hours of schedule development
- Start with a professionally organized scheduling framework
- Leverage 175 pre-built activities instead of creating a schedule from scratch
- Easily customize logic, durations, and calendars for your project
- Improve schedule consistency across drilling programs
- Ideal for planning, estimating, proposals, baseline schedules, and training
Software Compatibility
- Primavera P6 Professional
- Primavera P6 EPPM
- Primavera-compatible software supporting XER imports
Important Note
This template is intended as a planning framework and should be reviewed and modified to reflect project-specific drilling programs, client requirements, rig capabilities, calendars, operational procedures, and contractual milestones.
Instant Digital Download
Download the Primavera P6 XER file immediately after purchase and begin customizing your drilling schedule within minutes.
Also included with XER purchase is the following P6 Layouts:
· Longest Path
· Multiple Float Path
· 2 Week Update
· 4 Week Update
· 3 Month Look Ahead
· WBS Working Layout
NOTE: If you use multiple float path be sure to set your schedule options to multiple float paths.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.