The most complex logic begins with the Engineering logic that flows the the Model Review [30%, 60% & 90% Models]. Additional logic & details are linked to the procurement cycles which drive delivery to site for Construction and Commissioning.
Onshore Typical Level 3 Schedule XER Template [804 activities]
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Offshore Topsides & Platform Typical Level 3 Schedule Template [838 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
· Naval Architectural
· Transportation
· Hookup/Commissioning
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Offshore Deep Water Typical Level 4 Schedule Template [661 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic. This file is considered a Level 4 schedule ready with settings for utilizing Earned Value in Primavera P6.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Geotechnical & Geo Hazard
· Risk Management, VIP
· Design Safety
· Reliability Assurance & Integrity Management
· Project Manager/Engineering Manager
· Project Control Manager
· Project Administration
· Health, Safety, Security, and Environment
· Document Control
· Cost Control & Accounting
· Planning & Scheduling
· Quality Assurance
· Project Manager
· Design & Drafting
· Flowline Engineering
· Risers
· Production & Gas Export SCR Taper Stress Joints
· SPAR Onsite Pull Tube & I-Tube Drift / survey
· Subsea Controls
· Subsea Umbilical
· Flow Assurance
· Corrosion, ECA and Materials
· Interface Coordination
· SCR Pull Tube
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Subsea Typical Level 3 Schedule Template [1,051 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
· Naval Architectural
· Transportation
· Hookup/Commissioning
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Construction Fragnet Typical Level 3 Schedule Template [41 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Construction
· Pre-Commissioning
Detailed construction logic that flows through interdisciplinary logic that are linked to the Pre-Commissioning. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
EPC Onshore Mini Typical Level 3 Schedule [226 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic. This mini template has been by far the BEST SELLER.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
APA Primavera P6 Layouts
By a large demand, I have decided to sell my XER Layout templates for public use. Over all of my career, I have fine tuned and developed optimal P6 Layout Schedule Templates. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic. These layouts allow for fast analysis of your criteria.
Your purchased P6 Layouts native file package containsthe following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
Disclaimer: These layouts are intended to provide a majority start of your analysis of the schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their layouts based on their scope of work and needs of the project team.
Data Center Schedule - [372 activities]
Data Center Primavera P6 XER Template (372 Activities)
Stop building your project schedule from scratch.
This professionally developed Primavera P6 XER template gives planners, schedulers, project managers, and EPC professionals a structured starting point for developing data center construction schedules.
Whether you're bidding a project, creating an owner's schedule, or developing a contractor baseline, this template helps reduce schedule development time while providing a logical framework based on industry best practices.
Schedule Basis:
- Campus Area 80-120 acres
- Main Data Hall Building 250,000-350,000 SF
- Critical Load72 MW
- IT Capacity 60 MW
- Data Halls6 halls
- Hall Size 35,000-45,000 SF each
- Electrical Yard 8-12 acres
- Admin/Operations Building 15,000 SF
- Fuel Storage Area 10+ generator tanks
- Cooling Plant Central utility plant
What's Included
- Primavera P6 XER file
- 372 fully developed activities
- Complete activity logic and relationships
- Organized Work Breakdown Structure (WBS)
- Construction sequencing suitable for customization
- Milestones for major project phases
- Ready for import into Primavera P6
Ideal For
- EPC Contractors
- General Contractors
- Owners
- Project Controls Professionals
- Schedulers
- Planning Engineers
- Construction Managers
- Data Center Developers
Benefits
- Save hours of schedule development time
- Start from a proven scheduling framework
- Easily modify activities to match your project scope
- Improve consistency across projects
- Excellent learning tool for Primavera P6 users
Software Compatibility
- Primavera P6 Professional
- Primavera P6 EPPM (via XER Import)
- Primavera-compatible scheduling environments supporting XER files
Important Note
This schedule is provided as a planning template and starting point. Every project is unique and should be reviewed, validated, and modified to reflect project-specific scope, contract requirements, means and methods, calendars, procurement strategy, and construction execution plans.
Instant Digital Download
After purchase, download the Primavera P6 XER file immediately and begin customizing your project schedule.
Also included with XER purchase is the following P6 Layouts:
· Longest Path
· Multiple Float Path
· 2 Week Update
· 4 Week Update
· 3 Month Look Ahead
· WBS Working Layout
NOTE: If you use multiple float path be sure to set your schedule options to multiple float paths.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Drill Rig Schedule - [175 activities]
Onshore Drilling Rig Primavera P6 XER Template – 3-Well Pad Development
Develop quality schedules faster with this professionally developed Primavera P6 XER Template designed for a typical 3-well-pad onshore drilling project.
Featuring 175 professionally developed, logic-linked activities, this template provides a structured scheduling framework covering the major phases of drilling operations—from rig mobilization through drilling, casing, cementing, logging, rig release, and demobilization.
Whether you're preparing a bid schedule, developing a baseline, or creating a project execution schedule, this template provides an excellent starting point while significantly reducing schedule development time.
What's Included
- Primavera P6 XER file
- 175 logic-linked activities
- Organized Work Breakdown Structure (WBS)
- Complete activity logic and relationships
- Major project milestones
- Ready for Primavera P6 import
- Fully editable and customizable
Typical Scope
The schedule represents a typical onshore drilling program for a 3-well-pad development, including:
- Rig mobilization
- Rig-up and commissioning
- Surface drilling
- Intermediate drilling
- Production hole drilling
- Casing operations
- Cementing operations
- Directional drilling support
- Wireline logging
- Wellhead installation
- Rig-down
- Rig demobilization
- Project closeout milestones
Ideal For
- Oil & Gas Operators
- Drilling Contractors
- EPC Contractors
- Project Controls Professionals
- Planning & Scheduling Engineers
- Construction Managers
- Project Managers
- Consultants
Benefits
- Save hours of schedule development
- Start with a professionally organized scheduling framework
- Leverage 175 pre-built activities instead of creating a schedule from scratch
- Easily customize logic, durations, and calendars for your project
- Improve schedule consistency across drilling programs
- Ideal for planning, estimating, proposals, baseline schedules, and training
Software Compatibility
- Primavera P6 Professional
- Primavera P6 EPPM
- Primavera-compatible software supporting XER imports
Important Note
This template is intended as a planning framework and should be reviewed and modified to reflect project-specific drilling programs, client requirements, rig capabilities, calendars, operational procedures, and contractual milestones.
Instant Digital Download
Download the Primavera P6 XER file immediately after purchase and begin customizing your drilling schedule within minutes.
Also included with XER purchase is the following P6 Layouts:
· Longest Path
· Multiple Float Path
· 2 Week Update
· 4 Week Update
· 3 Month Look Ahead
· WBS Working Layout
NOTE: If you use multiple float path be sure to set your schedule options to multiple float paths.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.