The most complex logic begins with the Engineering logic that flows the the Model Review [30%, 60% & 90% Models]. Additional logic & details are linked to the procurement cycles which drive delivery to site for Construction and Commissioning.
Onshore Typical Level 3 Schedule XER Template [804 activities]
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Offshore Topsides & Platform Typical Level 3 Schedule Template [838 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
· Naval Architectural
· Transportation
· Hookup/Commissioning
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Offshore Deep Water Typical Level 4 Schedule Template [661 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic. This file is considered a Level 4 schedule ready with settings for utilizing Earned Value in Primavera P6.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Geotechnical & Geo Hazard
· Risk Management, VIP
· Design Safety
· Reliability Assurance & Integrity Management
· Project Manager/Engineering Manager
· Project Control Manager
· Project Administration
· Health, Safety, Security, and Environment
· Document Control
· Cost Control & Accounting
· Planning & Scheduling
· Quality Assurance
· Project Manager
· Design & Drafting
· Flowline Engineering
· Risers
· Production & Gas Export SCR Taper Stress Joints
· SPAR Onsite Pull Tube & I-Tube Drift / survey
· Subsea Controls
· Subsea Umbilical
· Flow Assurance
· Corrosion, ECA and Materials
· Interface Coordination
· SCR Pull Tube
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Subsea Typical Level 3 Schedule Template [1,051 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
· Naval Architectural
· Transportation
· Hookup/Commissioning
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
Construction Fragnet Typical Level 3 Schedule Template [41 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Construction
· Pre-Commissioning
Detailed construction logic that flows through interdisciplinary logic that are linked to the Pre-Commissioning. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
EPC Onshore Mini Typical Level 3 Schedule [226 activities]
By a large demand, I have decided to sell my XER templates for public use. Over all of my career, I have fine tuned and developed optimal Level 3 Schedule Templates. This logic has been vetted continuously by APA and is used as the primary starting template for all of our schedule development. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic. This mini template has been by far the BEST SELLER.
Your purchased XER native file package contains:
All activities that flow from Engineering to Construction Summaries & Commissioning
Summaries
· Engineering
· Procurement
· Subcontracts
· Fabrication
· Construction
· Commissioning
Fully detailed engineering logic that flows through deliverables and interdisciplinary logic that are linked to the Model Review. Disciplines include but not limited to:
· Process
· Mechanical
· Civil
· Structural
· Electrical
· Instrumentation
· Subcontracts
Also included with XER purchase is the following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
NOTE: Be sure to use the group and sort by Activity Code and NOT WBS. WBS is the most misused method in P6. I'm an old school scheduler and used Activity Codes to represent the WBS.
Disclaimer: Template is intended to provide a majority start of most schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their schedule based on their scope of work and reviewed/approved by the project team.
APA Primavera P6 Layouts
By a large demand, I have decided to sell my XER Layout templates for public use. Over all of my career, I have fine tuned and developed optimal P6 Layout Schedule Templates. APA has over 21 years building, evaluating, and developing schedules regarding EPC Logic. These layouts allow for fast analysis of your criteria.
Your purchased P6 Layouts native file package containsthe following P6 Layouts:
· Activity Type Check / Count
· Duration Type Check / Count
· Constrained Activity Review
· % Complete Type Check / Count
· Calendar Check / Count
· Longest Path
· Multiple Float Path
· 4 Week Update
· 90 Day Look Ahead
· S-Curve
· EVM – EAC Analysis
· WBS Working Layout [used to update EVM]
· No Actual Finish & % Complete =100
· Actual Start & no % Complete started
· Actual Finish & % Complete <100
· Expected Finish > Data Date
Disclaimer: These layouts are intended to provide a majority start of your analysis of the schedules. This is not a copy/paste for your projects. It is the responsibility of the planner/scheduler/project team to customize their layouts based on their scope of work and needs of the project team.